Demolition of the Clark Street structure above 15th Street South in Crystal City starts Monday, July 16. This work requires periodic eastbound and westbound detours on 15th Street at Clark Street and Route 1. Detour details: July 16 - 17: Detour on eastbound 15th Street South; July 18 - 26: Detour on westbound 15th Street South. Hours for the demolition work will be 7 am to 5 pm each weekday. The bridge structure will be removed in sections. No explosives will be used.
Between July 18 and July 26, the ART 43 bus stop at the VRE Station (18th and Crystal Drive) will be closed due to construction on South Clark Street. If you use the ART 43 route, you should board the bus at Crystal City Metro (Bus Bay A) during this time frame. Read More

Pentagon Centre PDSP

Pentagon Centre

In 2008, the Arlington County Board approved a Phased Development Site Plan (PDSP) for Pentagon Centre, a high density, mix-used complex in Pentagon City. The approval was revised during the summer of 2015 to reflect changing market conditions and to reallocate the phasing of the project. The revised first phase of the PDSP allows current retailers such as Costco, Marshalls and Best Buy to exist while incorporating two new residential buildings that include additional retail, and a stand-alone above-grade parking garage(completed in late 2016)to serve Costco. The development aligns with the County's strategic priorities of smart growth, multi-modal transit options and green buildings.

Highlights:

  • 1.962 million square feet of new development
  • 705,000 square feet of new commercial office space in three new buildings
  • 346,600 square feet of new retail space
  • 693 residential units
  • 200-room hotel
  • Inclusion of approximately 3.17 acres of new, dedicated open space

First Phase Highlights:

  • 25-story residential building comprised of 440 units and about 10,000 square feet of ground floor retail
  • 10-story residential building comprised of 253 units and over 15,500 square feet of ground floor retail
  • Parking garage: 7-story parking structure with over 8,850 square feet of ground floor retail

Schedule:

  • PDSP Approved by County Board in 2008
  • Amended PDSP Approved by County Board in
  • Parking Garage Structure Completed in late 2016
  • Construction of 440-unit apartment building initiated in early 2017

Additional info: